Location
Hamersley Ranges, Pilbara, Western Australia
Client
Roy Hill
Contact
The Roy Hill Ultrafines Stage 2 Project forms part of Roy Hill’s project pipeline to identify recovery improvement and expansion projects to be able to consistently achieve the approved export capacity of 60Mtpa. BGER has completed an Engineering and Cost Study for the UF 2 Project. The project is still in progress and subject to confirmation of test data currently in progress. Project risks and opportunities are being progressively captured and the design allows for optimisation of layouts and equipment confirmation planned for the value engineering phase.