Location
Pilbara, Western Australia
Client
Undisclosed
Contact
A global mining giant engaged us after discovering that three existing mooring dolphins at one of its fuel wharves were in poor condition with significant corrosion to the steel above the water line.
Our specialist Ports & Marine team was quick to respond, undertaking a priority site visit within a couple of days. Timing was of the essence as the wharf was in the midst of undergoing refurbishments and upgrades.
On arrival, our professionals visually inspected the condition of the existing dolphins, performed a dive inspection of the piles below the water level, and undertook thickness testing. They also conducted an analysis of the existing dolphins to determine utilisation and assess remaining life.
Following this, we delivered a range of design services to enable repairs including electrical, hydraulic and civil engineering.